From the File menu, select Company Settings > Divisions tab.
Or, click on the Company Settings icon within the File toolbar and select the Divisions tab.
Click the drop-down arrow in the Division field.
Click on the division to edit.
To delete a day from the work week for the division, click the checkbox associated with the day to delete. The checkbox should be blank.
To delete an existing work week completely from the division, click the checkbox to the left of each day, and leave every checkbox blank.
Click Save at the bottom of the Divisions screen to save any changes.
Click Close to exit the screen.
|
Note |
|
If the client has defined the work week at the company level (See the Defining the Company Work Week) to be Monday through Friday, and the division work week needs to include Saturday, the checkbox for each day of Monday through Saturday will need to be marked. If only Saturday is marked at the division level, the work week will calculate within the schedules for Saturday only. |
|
Note |
|
The Work Week may also be set at the Company, Area, or Job level. When calculating dates within schedules, the Scheduling module will look first to the work week at the Job level, second to the work week at the Area level, Third to the work week at the Division level, and last to the work week at the Company level. Within this hierarchy, the first completed work week that is found will be used to calculate the dates within the schedule. See Working with the Company Calendar, Setting up Jobs - Scheduling Only, (or Setting Up Jobs - Timberline Integration), and Setting Up Areas. |
Defining the Division Work Week
Adding Days to the Division Work Week