Approve a Partial Payment of a Purchase Order

The instructions below outline how the user can approve a partial payment purchase order. When approving purchase orders in this screen, the user can use the <Tab> key to move through the fields.

To approve a partial payment of a purchase order:

Note

Partial payment of a purchase order will only be allowed if the user has been assigned the privilege to approve partial payments. See Working with User Management for more information.

 

 

 

 

 

  1. From thePurchasing menu, selectApprove Payment of Purchase Orders.

  2. Click on the Part Pay icon in the screen's toolbar.

  3. Click on the Show Invoice History icon.

The screen displays three distinct sections as shown:
 

 

 

Notes

Once the Part Pay icon and/or the Show Invoice History icon are selected, the screen remains split into three distinct sections as the user moves between purchase orders and continues to process both full and partial payment approvals. The user may choose to leave all three screens open while approving, or choose to close the Part Pay Details section and/or the Invoice History section at any time during the approval session. To close the Part Pay Details screen, click the Part Pay  icon. To close the Invoice History screen, click the Show Invoice History  icon.  

 

 

  1. Accept the Default Completion Date, or click on the drop-down menu to select an alternative date in the drop-down calendar.

  2. Accept the Default Accounting Date or click on the drop-down menu to select an alternative date in the drop-down calendar.

  3. If the Default Accounting Date is to be applied to all approved invoices during the current application session, click on the Apply Default Accounting Date to All Approved Invoices icon.

  4. If tracking invoices by draw numbers, enter the appropriate draw # in the Draw # field.

  5. If the draw # is to be applied to all approved invoices during the current application session, click on the Apply Draw # to All Approved Invoices icon.

  6. Select either of the following payment methods explained in the following instructions, partial payment by line item or partial payment approval by invoice net amount.

 

To approve a partial payment by line item:

  1. Select the purchase order to approve.

  2. Within the top section of the screen, click on the specific purchase order number. The line item detail for the selected purchase order will now display in the Part Pay Details section in the middle of the screen.

  3. To select the line item to be approved, click on the line item. The entire line will now be highlighted.

  4. Select the appropriate amount to approve.

As the user enters information on each line item in the Part Pay Details section, the approved percentage will automatically calculate and will display in the % Approved to Date field for the line item, as shown above. The invoice net total amount will be incremented in the Part Pay Details screen. The Invoice Net Amount field for the selected purchase order in the top section will also be incremented to reflect the total of the approved amounts on each line item.

 

To approve a partial payment approval by invoice net amount:

  1. In the top section of the screen click in the Invoice Net Amt field for the specific purchase order.

The cursor will be flashing in the Invoice Net Amt field, and the line item detail for the selected purchase order will now display in the Part Pay Details section in the middle of the screen.

  1. Enter the total amount of the partial payment in the Invoice Net Amt field, and press the Enter key.

  2. Enter the invoice number for this purchase order, if available, in the top section of the screen. The invoice number is used to track the payment through the Sage Timberline® Office Accounts Payable system.  

  1. Click Save.

 

Understanding the Date Fields

 

Date Completed

This is the date the scheduling activity was completed or the date the purchase order was approved for payment. If the Approve Remaining checkbox is selected, this field defaults to the current date.

Invoice Date

This date defaults to the default completion date from the Approve Payment of Purchase Orders screen. The user can overwrite this date as necessary.

Payment Date

Date the invoice is due to the supplier

Discount Date

Date the invoice must be paid by in order to have the discount applied

Accounting Date

This date controls which General Ledger period in Sage Timberline Accounting that cost is posted to.

Approved To Date

Total dollar amount of invoices approved for payment for the purchase order.

 

 

Related Topics