Set Up Job Cost Category Types

 

The Category Type determines how purchase orders are issued after the budget has been finalized in Sage Timberline® Office Job Cost. Once the budget is finalized, only certain Category Type costs are allowed to be issued on purchase orders and committed in Job Cost. This function is only applicable if the Finalize Budget function is activated and used in Job Cost.

 

IMPORTANT

After adding a database to the list of Accounting databases, it is necessary to complete the set up of Job Cost Category Types for each database in the list.

 

 

 

Understanding Job Cost Category Types

Categories are additional classifications/divisions of costs incurred, and provide a method to track costs in Sage Timberline® Office Accounting. Categories also facilitate cost analysis in the Sage Timberline Office Job Cost module. Categories allow the user to track estimates, actual costs, and other important information at a sub-level below cost codes. For example, one of the cost codes might involve concrete forming, and it is necessary to distinguish labor costs from material costs. This can be accomplished by setting up one category for labor and another for materials. Both types of cost can be reported separately as labor and material at the category level. Both costs combined can be reported as concrete forming at the cost code level. Categories are generally set up in Sage Timberline Office Job Cost, and imported into the WMS database. See Update All Timberline® Files for additional information.  

 

Note

In order to verify the most up-to-date list of Job Cost Categories is available in WMS, import the information from Sage Timberline Office Accounting prior to setting these options.

See Update All Timberline Files for additional information. Verify that the Job Cost categories match exactly with the standard categories in Sage Timberline Office Job Cost.

 

 

There are 6 default categories available in the Purchasing module:

 

To set up Job Cost category types:

  1. Verify the database currently active is the one for which the Job Cost Category types need configuring. (This is the database currently open for the division.)

  2. From the Integration menu, selectTimberline Accounting > Set Up Job Cost Category Types.

 

The following screen displays.

 

 

A complete list of all Job Cost Categories, their descriptions and JC Cost Types will display on this screen. This list reflects the information up through the most recent date the Update All Timberline Files process has been run. The left-hand columns are for information only, and cannot be edited in this screen.

 

  1. Click the Category Type drop-down menu to display the Job Cost Category options.

The description for each Category Type follows:

  

Base/Original Cost

 

Note

This process will not function correctly if the budget has been finalized in Sage Timberline Office Job Cost prior to all of the base cost purchase orders being issued.  If purchase orders are issued in multiple releases, the budget can not be finalized in Sage Timberline Office Job Cost until after the final release has been issued.

 

 

 

 

 

 

 

 

Change Order

Non Billable Variance

Blank (Null)

  1. Select the categories whose budgets should be sent to Job Cost. This setting will now include BOTH the former Cat 'O' budget and Variance budget to Accounting described below.

  1. Select the categories whose purchase order commitments should be sent to Job Cost.

  1. Choose whether or not to print prices on purchase orders. Selecting this checkbox will include BOTH the former Cat 'S' and Cat 'O' amounts described below.

  1. Click within thePrint PO if all this Cat checkbox to allow a purchase order to print even if all items are assigned a job cost category of ‘O.’

  1. Click within the Default CO Cat checkbox to assign a default cost category to all change orders received from the Sales Center and to any manually issued change orders (created in the Purchasing module) not assigned a specific category. This provides a method of tracking costs in Job Cost for change orders separate and distinct from the original budgeted costs.

 

Checkbox in New JC Category Setup

Former WMS Global Setting

Budget to JC

(allows budgets to transfer/not transfer to Accounting)

Global Settings > Accounting Integration > Send to Timberline Accounting Options > Send Cat 'O' Budgets to Accounting and Send Variance Budgets to Accounting

Commitment to JC

(allows purchase order commitments to transfer/not transfer to Accounting)

Accounting Integration > Send to Timberline Accounting Options > Send Cat 'O' Commitments to Accounting

Print Prices on PO

Global Settings > Purchasing > Purchasing tab > Print Cat S (Sub) Amounts on PO and Print Cat O (other) amounts on PO

Print PO if All this Cat

Global Settings > Purchasing > Purchasing tab > Print PO where all items are ‘Cat O’

Default CO Cat

 

Global Settings > Purchasing > JC Categories tab Default CO JC Category.

 

  1. Once finished with all changes, click Save.

  2. Click Close to exit the screen.

 

Related Topics

Finalizing the Budget in Sage Timberline Office Job Cost

Issuing Budgets if Budgets are Finalized in Sage Timberline Office Job Cost

Issuing Purchase Orders if Budgets are Finalized in Sage Timberline Office Job Cost

Update All Timberline Files

Share All Job Information with Job Cost

Receive New Jobs from Job Cost

Field Mapping to Timberline

Receive All Suppliers from Accounts Payable

Receive New Suppliers from Accounts Payable

Receive Tax Tables from Accounts Payable

Receive Controls from Accounts Payable

Receive Cost Codes from Job Cost

Receive Cost Categories from Job Cost